The main goal of the project was to optimize a 25MW biomass cogeneration plant. The client sought out our expertise to guide them through the optimization process in order to reach their efficiency goal. BMA’s mission was to improve maximum capacity while taking into account various operating parameters of the existing installation (biomass, humidity, volatile particles, ash, clinker, etc.), and to support the client in several re-hauls of specific components, thus optimizing combustion.
Preliminary and detailed engineering
On Site Assistance
Testing and start up of various solutions
Performance reports